MOTORISTS are being warned to allow extra time for their journeys as work continues on the River Ceiriog Viaduct on the A5/A483 bypass.

The works include the demolition and re-construction of the reinforced concrete viaduct where it joins its support on the southern side of the Ceiriog Valley.

Today (Thursday) the works were progressing well, with the hydro demolition phase nearing completion.

A5 River Ceiriog Viaduct Works Progress. Traffic Wales

A5 River Ceiriog Viaduct Works Progress. Traffic Wales

Image: Traffic Wales

The old joint has been removed and the new joint had arrived on site ready to be lifted in to place.

Work began on February 22 and are programmed to take eight days.

Built in 1990, the viaduct spans 500m from the northern side of the Ceiriog Valley in Wales to its southern side in England. After 30 years, the large expansion joint at the southern end of the viaduct is reaching the end of its operational life and must be replaced.

Planned routine maintenance and bridge investigation works will also take place to make the most of the closure. Highways England will also carry out work on their section of the road between the southern end of the viaduct and the Gledrid roundabout.

There have been traffic delays caused by the diversions, but Traffic Wales North and Mid said the dates had been chosen to minimise disruption.

Traffic flow.

Traffic flow.

Image: Traffic Wales

Traffic Wales tweeted: "We know getting delayed by roadworks can be frustrating, but these works are essential to ensure motorists’ safety. Weekly traffic flows are down approximately 40% compared to this same time last year at this location.

"We’re taking advantage of the lower than average traffic levels so we can deliver this vital work while reducing the impact on travel times.

Planning for the work was agreed with Wrexham and Shropshire Councils.

Ahead of the scheme, Transport Minister Ken Skates said: "It is essential that this work is carried out to maintain the condition of the A5 River Ceiriog Viaduct. Every effort is being made to minimise disruption as much as possible and to complete the work as quickly as possible.

"Planned full closures of carriageways are never taken unless they are absolutely necessary, but the safety of the travelling public is paramount and this work needs to take place to ensure that.

"I would urge the travelling public to follow the diversion route signage while this work is in progress, and I thank them and local residents for their co-operation and patience."